DESCRIPTION OF PROJECT

The Lightsview basins consisted of partially complete basins that were excavated two years prior to T&J Constructions commencing on site so the development to the north and east of the basin could continue. T & J Constructions were engaged to complete the additional excavation to increase the size of the basin, complete the clay liner and all associated stormwater works.

KEY CONSTRUCTION PROCESSES

  • Excavate out material with excavator and dump truck.
  • Complete all stormwater pit and pipe works
  • Detailed excavation of basin floor with GPS 30T excavator with tilt bucket
  • Rip and moisture 200 mm clay layer insitu
  • Import and spread 200 mm clay layer under level 1
  • Spread 200 mm topsoil on clay layer
  • Pump ground water out of basin

LOCATION

Lightsview, South Australia

CONTRACT VALUE

B $620,000
C $600,000
D&E $278,037

CONSTRUCTION PERIOD

B – 2019 12 weeks
C – 2019 12 weeks
D&E – 2020 8 weeks

CLIENT

CIC Northgate Pty Ltd