DESCRIPTION OF PROJECT

This project involved using bulk earthworks to construct a detention basin along the northern expressway, in order to protect the roads from flooding and erosion. Using a small fleet of large plant, T & J Constructions moved 200,000 cubic meters of earth within 10 weeks, in the middle of winter.

KEY CONSTRUCTION PROCESSES

  • Removal of existing trees and vegetation.
  • Earthworks to create basin banks & floor.
  • Excavation of low flow channels.
  • Construction of access tracks and ramps.
  • Smith Creek Bulk Earthworks.
  • Installation of Reno Mattress.
  • Installation of Gabions.
  • Installation of Scour Protection Rock.
  • Stormwater pit & pipe installation.
  • Stormwater headwall installation.
  • Landscaping; planting low flow channel & spraying seed

LOCATION

Penfield, South Australia

CONTRACT VALUE

$3,050,000

CONSTRUCTION PERIOD

March 2017 – August 2017

CLIENT

City of Playford